Project Overview:
Hamilton executed the installation, testing, and commissioning of a new Hazardous Area Dust Filter Unit at AGL’s Wallumbilla Gas Plant. The project involved careful planning and coordination to ensure compliance with stringent hazardous area requirements and seamless integration with existing plant systems.
Project Highlights
This project required meticulous attention to complex hazardous area considerations, with the Hamilton team collaborating closely with mechanical contractors to complete the work within a tight shutdown window. Despite last-minute changes to the earthing configuration for enhanced maintainability, the team delivered the project on time and within budget, demonstrating their commitment to flexibility and precision.
Project Statistics
1 Month
Project Duration
$80,000.00
Project Value
350
Man Hours