Project Overview:

Hamilton successfully designed, procured, and constructed a new control system for the Gympie Regional Council’s Cooloola Cove Water Treatment Plant. This comprehensive project included the design and construction of a new control panel, the supply and installation of electric actuated butterfly control valves, and the development and integration of new PLC code (Allen Bradley) and SCADA mimics (Clear SCADA). Additional works included trenching and installing underground services, followed by thorough testing and commissioning on-site.


Project Highlights

The Hamilton team demonstrated exceptional adaptability throughout this project, overcoming numerous unknowns discovered along the way. Our skilled system integrators implemented adjustments and refinements to ensure the delivery of a robust and reliable system, tailored to the plant’s unique requirements.

Project Statistics

9 Months

Project Duration

$300,000.00

Project Value

400

Man Hours